Defense Logistics Agency’s Year 2000 Program
Managing Organization-Wide Conversion and Compliance
Sarah J. Reed Defense Logistics Agency System Design Center The Defense Logistics Agency considers the year 2000 (Y2K) problem mission-critical, and we have treated itas such in planning and executing the largest maintenance effort we have undertaken. The agency kicked offa formal Y2K project in November 1995 with nearly a full year of planning, preparation, and piloting. Thisarticle discusses our Y2K initiative and our experiences in raising awareness and in assessing, renovating, andvalidating our systems. Our program, built on available industry research and our experiences, has beenmodified as we have gained fresh insight and assimilated new lessons learned.
The Defense Logistics Agency interview and survey. Responses were developing funding proposals, conver-
consistency, then queried and analyzed.
and tools to facilitate analysis, renova-
tion, and testing. Conversion progress is
assessed on a regular basis through status
date references are high impact; that is,
sulted in a fairly comprehensive applica-
automated information systems (AIS). Expected to be rehosted,
for-service activity, and funded as we are
reengineered, or replaced but not Our Application Profile compliant (16 percent, 19 applica- tions). If replacement initiatives experi-
ponent data provides an idea of our size:
across multiple system structures. The
Component Total number
systems has been for us, unprecedented.
replacement system initiatives experience
System Impact Assessment Findings, Recommendations, and Resulting Actions
tions about date practices, levels of cus-
Expected to remain in place be- yond 2000 and compliant (33.6 per- cent, 40 applications). Systems thought Expected to remain in place be- yond 2000, but not compliant (47.1
less risk than those that were not compli-
percent, 56 applications). We ad- CROSSTALK The Journal of Defense Software Engineering 11 Year 2000
worked to establish a liaison with ourchief deployment site. Vendor Product Risk Related Observations and Date formats. The wide variety of Assessment and Mitigation Recommendations AISs not included in the survey data.
points out the need for greater standard-
survey for a variety of reasons, e.g., they
always practical for large, complex legacy
straints associated with them. Because of
• Enter response data into a repository. Database Management Systems
• Analyze for risk classification. (DBMS). The 15 different database Vendor product compliance. The
discovered that having a date field with a
gram office continues to pursue the issue
publish its findings along with appropri-
Awareness. In spite of briefs to senior Interface recommendations. Initially, Identification of Development Environment Software
the initiative in January 1997. We subse-
rums to facilitate the sharing of progress,
the system and filter building to protect
Assessment process. We knew going
into the assessment process that develop-
ing data—and not on self-initiated inter-
expected to find a similar identification
agree that an interface strategy was nec-
analyzing the results would be a difficult
not to change the interface formats until
statistical analysis or survey science back-
were not previously identified by the
application support areas or the acquisi-
strategy was delivered in August 1997.
the quality of the survey responses, often
tion office. We established possible rea-
Release Management. AIS upgrades
are normally released to multiple deploy-
sented the additional challenge of simul-
Where Are We Now? 12CROSSTALK The Journal of Defense Software Engineering Defense Logistics Agency’s Year 2000 Program: Managing Organization-Wide Conversion and ComplianceFollow up with vendors expected to provide compliant products at a future date. For these products, we
dor to obtain the required information. Develop testing strategies for those products vendors have stated are com- Improve software portfolio man-
their application. Upgrade strategies will
pliant. Ascertaining the state of vendor agement processes. The great discrep-
timely arrival, installation, and testing of
Develop independent strategy for IBM products. A planned operating
published studies still leaves a vulnerabil-
Table 1. Y2K support tool categories according to DLA internal priorities.
f rt via the automated generation of test data
r ss-centur ,y and next century test cases.
advance dates in test data transactions.
Ability to simulate dates other than cu e
o r priority; our strategy utilizes expansion on limited basis
CROSSTALK The Journal of Defense Software Engineering 13 Year 2000
in Table 1. The higher priority tools (1,
Review and Selection of
2, 3, etc.) are those tools for which little
sometimes difficult to get it installed. Support Tools
or no existing internal capability existed
Tool Recommendations and Implementations
tify potential tools and determine appro-
Certification Process to Benchmark and Report System Compliance
dural logic or date windowing solution. Lessons Learned
Table 2. Characteristics of six DLA Y2K conversion projects.
f r UNIX shel , C modifications. In-house-
14CROSSTALK The Journal of Defense Software Engineering Defense Logistics Agency’s Year 2000 Program: Managing Organization-Wide Conversion and ComplianceRenovation. The selected approach
different certification levels reflecting
Certification Process
approach is the only risk viable approach
to achieving Y2K compliance in time. Awareness and Communications. A
certification guidance and a checklist.
to presentation to the customer for final
Pilot Project Study
the user-interface layer. It is important
for the user to understand the impacts of
Lessons Learned
various system, interface, and user inter-
• In spite of our efforts to streamline it,
• Identification of not-yet-anticipated
ure risk to the existing system. Addition-
ally, intention to replace a legacy system
does not entirely relieve the customer of
tions and additional testing and certifi-
Pilot Project Profile
cation activities may still be required to
Table 2 summarizes the characteristics of
been, and continues to be, difficult. Lessons Learned Estimation of the Effort Involved.
effectively used by all pilots. To compen-
pilot project lines of code (LOC) costs. Tools. In-house tool capability was
• In spite of our best efforts to baseline
CROSSTALK The Journal of Defense Software Engineering 15 Year 2000 • Focus on the underlying hardware
during pilot testing efforts. This realiza-
tion from pilot efforts escalated our tool
• Obviously, remediation for systems
assessment and procurement initiatives. Testing. Testing time and effort was
planning within the system effort,
Provide Sufficient Investment in
even as the system is being renovated. • Carving out enough time for inte-
tools and training, without effective test
cient to ensure success of the effort.
in testing procedures within the organiza-
tion affected attempts to baseline a certifi-
expertise to guide the test plan develop-
cation process. Effort expended in defin-
About the Author
ing Y2K-specific testing practices and in
Sarah J. Reed began
strategy for specific needs related to test
Be Prepared for High-Level
environments, test tools, test utilities,
Visibility
We recognize the benefit of high visibil-
ity as the crucial components of sponsor-
the Organizational Culture Initiative, and
Release Management. Close coordi-
tool releases but also for a larger-than-
she led the effort to establish a baseline
leases into the field. Where file conver-
these calls for information. Lack of such
Observations and Conclusions
sons learned as they pertain to significant
have found to be the most critical factors
aspects of our effort. Here we offer some
overall observations and conclusions. • Sustaining organizational commit-
Provide a Sufficient Resource • Understanding the organizational
Voice: 614-692-9296 DSN 850-9296Fax: 614-692-8393 DSN 850-8393
Investment
baseline at the outset of the initiative. • Understanding the challenge in ap-
• The adequacy of testing tools and16CROSSTALK The Journal of Defense Software Engineering
ministero per i beni e regione siciliana comune Di le attività culturali ass. reg. turismo caltanissetta sport e spettacolo ASSOCIAZIONE AMICI DELLA MUSICA 44° CONCORSO INTERNAZIONALE «VINCENZO BELLINI» PER CANTANTI LIRICI FOR OPERA SINGERS - POUR CHANTEURS LYRIQUES 1 - 6 DICEMBRE 2013 Ministero dei Beni e delle Attività Culturali Musica dal
Journal of Exposure Science and Environmental Epidemiology (2007), 1–8r 2007 Nature Publishing Group All rights reserved 1559-0631/07/$30.00Pesticide loadings of select organophosphate and pyrethroid pesticides inurban public housingRHONA JULIENa, GARY ADAMKIEWICZa, JONATHAN I. LEVYa, DEBORAH BENNETTa,b,MARCIA NISHIOKAc AND JOHN D. SPENGLERaaHarvard School of Public Health, Harvard Universi